Our Rainer Square sites are currently in full swing with all phases of construction taking place on the various projects. On the Shell & Core Tower Project, we are entering the last 10% phase which includes start-up, commissioning, and test and balancing activities of equipment throughout the tower’s 60 floors.

On the Residential & Amenities TI Project, overhead and wall rough-in activities are quickly approaching the residential penthouse floors and finish activities are just beginning to take place on the lower residential levels.

On Levels 39 and 40, which are the shared amenities floors that serve the residential units, layout and overhead rough-in activities are just beginning which represent the last remaining major activities on the project.

Lastly, the 400U Project which is a 12-story office building just south of the new Rainer Tower is placing the cast-in-place concrete core wall and working through MEP coordination activities. The Rainer Square Shell & Core and Residential Projects are scheduled for substantial completion near the end of this year; 400U is aiming for completion in June of 2021.

Read our latest Perspective Newsletter 

Categories: General

We make buildings work better.